Observation on Overtrawlable Structure
and Christmas Tree Deployment
EV Offshore Ltd supply Sacrificial
Cameras and Monitors and camera technician to operate and maintain EVOLeye® CS
Subsea Inspection System for overtrawlable structure and Christmas Tree deployment
on British Gas Apollo Field.
February/March
2003, Labrador 1 Jack-Up Rig, North Sea, Blocks 42/28 and 47/2 and 3.
EV
Offshore sacrificial cameras and top side monitors, CCTV System and EVOLeye® CS
were used extensively as to assist in deployment of subsea overtrawlable
structure and christmas tree on the Apollo A1 well in the North Sea.
Project
overview
The
operation involved the deployment of an overtrawlable structure onto the seabed
wellhead, followed by the mounting on the structure of the christmas tree.
Preliminary
Operation – Pick-up of structure from supply vessel.
Equipment used Portable
CCTV System
The overtrawlable structure was to be lifted from the supply
vessel using a tool attached to a drill string. The lift for the driller was blind, so the 2 CCTV cameras were
mounted in positions that allowed telephoto and wide views of the supply vessel
during the pick-up and lift to the Texas deck.
The zoom function allowed a clear view of the deck of the supply vessel,
a wide view was ideal for giving the driller the wider picture.
Secondary
Operation – Deployment of Structure to Seabed.
Equipment used Sacrificial
Camera System, 2 cameras operational
External
Halogen Lights
EVOLeye® CS
Camera System
Two sacrificial cameras with halogen lights were mounted to the
underside of the structure on custom brackets that had been pre-fitted. The cameras were mounted at 90B to each other, one focused on the lead-in funnel of the
structure, the other angled slightly downwards to view first sight of the approaching
wellhead. Painted on the funnel was a
datum line that aligned with a keyway and a similar line painted on the
wellhead. A switching break-out box was
mounted onto the structure with a weak-link to the umbilical.
The
picture shows the 2 sacrificial cameras test fitted onshore viewing the funnel
prior to deployment offshore.
The
EVOLeye® CS pan & tilt camera was mounted on the tool of the BHA that was
J-fitted to the structure. The camera
was positioned to view the hydraulic locking latch indicator and also the view
of the J-slot.
As
the structure was lowered and approached the wellhead, the sacrificial cameras
were used to guide the driller to position the structure in exactly the right
orientation to line up with the wellhead such that the key and keyway lined
up. By switching between the
sacrificial cameras, an accurate 2-axis position of the structure could be
achieved, thus allowing a smooth positioning on the wellhead.

A
hydraulic locking latch was operated from topside, which locked the structure
to the wellhead. The latch was
continually observed by EVOLeye® CS to confirm the latch had travelled full
distance. An over-pull by the drawworks
confirmed the latch. The pan & tilt
camera module on EVOLeye® CS was repositioned to assist the driller in removing the
BHA from the J-s-slot.
The
picture clearly shows EVOLeye® CS’s camera that allows views of the latch indicator
(painted black and orange) in the ’retracted’ and ‘locked’ positions.
The
entire BHA was pulled out of hole to surface, leaving the sacrificial cameras
on the structure, their job completed successfully.
Tertiary
Operation – Deployment of Christmas Tree to Structure.
Equipment used Sacrificial
Camera System, 3 cameras operational
External
Halogen Lights
Three
sacrificial cameras were mounted on the christmas tree to perform a similar
function to those on the structure. One
camera was mounted on the underside viewing the lead-in funnel; one was mounted
on the side with a full view of the manifold block and hydraulic flow line; the
third camera was mounted on the hydraulic locking latch. A 3-way camera break-out box was also
mounted on the tree with the umbilical weak-link.
On
deployment, the lead-in funnel and flowline observation cameras were
continually monitored to aid landing the tree, and also ensuring that the
hydraulic flowline adequately cleared the side members of the overtrawlable
structure.
When
the tree was landed, the third camera was used as verification that the
hydraulic latch had travelled its full seating distance. A drawworks over-pull confirmed the tree was
locked in position on the structure.
The
umbilical weak-link was severed on pulling out of hole, and once again the
sacrificial cameras remained on the seabed after their successful deployment.
More information on this application and other
camera system and instrumentation can be obtained from EV Offshore, please
follow this link <contacts>